Representation Summary:

Acceptable subject to access via A1270 Broadland Northway roundabout at Norwich Airport. Improvements required at the roundabout to formalise access to site, along with relocation of access gates to provide sufficient space for 2 HGVs to stop clear of the roundabout. Relocation of processing plant to south of C250 Church Lane required. Removal of HGV access at Buxton Road also required.

Full text:

Original draft response received 30.10.2019
Revised response received 08.11.2019

Highway Authority comments regarding sites proposed for allocation only

MIN 12 - North of Chapel Lane, Beetley
Acceptable subject to continued use of conveyor

MIN 51 & MIN 13 - West of Bilney Road, Beetley
Acceptable subject to suitable access strategy. MIN51 to be accessed via MIN13

MIN 200 - West of Cuckoo Lane, Carbrooke
Acceptable subject to provision of acceptable access at Mill Lane along with provision of passing places between the site and the B1108. Existing haul route and Mill Lane crossing to processing plant to be utilised, or appropriate alternative to be provided. Routing agreement required along with weight limit to protect Carbrooke settlement north of the site.

MIN 202 - South of Reepham Road, Attlebridge
Acceptable subject to use of existing access at Reepham Road and lorry routing via A1270 Broadland Northway

MIN 37 - Mayton Wood, Coltishall Rd, Buxton
Acceptable subject to provision of satisfactory temporary access at C494 Coltishall Road with acceptable visibility. Local highway improvements including widening required, to be delivered via S278 agreement. Temporary access to be removed on restoration of site. Routing agreement required.

MIN 64 - Grange Farm, Buxton Rd, Horstead
Acceptable subject to provision of satisfactory temporary access at C494 Coltishall Road with acceptable visibility. Local highway improvements including widening required, to be delivered via S278 agreement. Temporary access to be removed on restoration of site. Routing agreement required.

MIN 65 - North of Stanninghall Quary
Acceptable subject to access via existing site and routing agreement.

MIN 96 - Grange Farm (between Spixworth Rd & Coltishall La), Spixworth
Acceptable subject to access via A1270 Broadland Northway roundabout at Norwich Airport. Improvements required at the roundabout to formalise access to site, along with relocation of access gates to provide sufficient space for 2 HGVs to stop clear of the roundabout. Relocation of processing plant to south of C250 Church Lane required. Removal of HGV access at Buxton Road also required.

MIN 213 - Mansom Plantation, Stratton Strawless
Acceptable subject to acceptable access at Shortthorn Road and routing agreement via A140.

MIN 206 - Oak Field west of Lynn Road, Tottenhill
Acceptable subject to access via land to north, then A10. Routing agreement required.

MIN 69 - North of Holt Road, Aylmerton
Acceptable subject to provision of right hand turn lane at A148 junction with Briton's Lane, visibility improvements at site access, improvements to Britons Lane and routing agreement, in accordance with the existing allocation.

MIN 115 - Lord Anson's Wood, North Walsham
Acceptable subject to site access being via private haul route to acceptable access at B1150

MIN 207 - Pinkney Field, Briston
Acceptable subject to continuation of existing haul route

MIN 208 - South of Holt Road, East Beckham
Acceptable subject to access via existing right turn facility. Right turn lane to be removed following completion of extraction/restoration.

MIN 209 - Adjacent to A143 (Extension Area 1), Earsham
Acceptable subject to appropriate highway access and local highway improvements at Hall Road

MIN 210 - Adjacent to A143 (Extension Area 2), Earsham
Acceptable subject to site access via Site MIN 209 along with any appropriate improvements to the local highway at Hall Road and the site access. Material conveyor required.

MIN 211 - West of Bath Hills Rd (Extension Area 2), Earsham
Acceptable subject to site access via Site MIN 209 along with any appropriate improvements to the local highway at Hall Road and the site access. Material conveyor required.

MIN 25 - Manor Farm (between Loddon Rd & Thorpe Rd), Haddiscoe
Acceptable subject to suitable access strategy either via Crab Apple Lane, or direct to B1136. Access via Crab Lane would require local highway improvements to include widening to the access and visibility at the B1136 junction in accordance with DMRB. Direct access via B1136 to include visibility in accordance with DMRB.

MIN 212 - Mundham Rd, Mundham
The Highway Authority would not wish to comment regarding the proposed mineral extraction site. However, the location of the processing site is a concern and in particular the routing of HGVs through Trowse village. It would be desirable if the material could be processed at source.

MIN 6 - East Winch Rd, Mill Drove, Middleton
Acceptable subject to use of internal haul route, existing processing facilities, acceptable visibility at access and routing agreement. The allocation would result in a continuation of turning movements at the A47, Highways England should have the opportunity to comment.

MIN 40 - East of Grandcourt Farm, East Winch
Acceptable subject to material processing at existing plant, use of existing internal haul-route required and continued use of rail for material transportation.

SIL 01 - Mintlyn South, Bawsey
Acceptable subject to extraction phased with MIN 40, submission of Transport Assessment with acceptable access strategy. Material transportation to existing processing plant via internal haul route and acceptbale crossing / conveyor of highway and utilise existing rail facilities.

AOS E - North of Shouldham
Subject to submission of Transport Assessment including delivery of acceptable highway improvements. Access to be via A143 with right turn lane with suitable levels of visibility. Access via West Briggs Drove would not be appropriate without significant improvement. Movement of material using off-highway routes, or conveyor/pipeline etc. preferred. Should material be conveyed by highway, a suitable access to the processing facility shall be provided shall be provided at B1145, to an acceptable standard including visibility. Highways England should be consulted regarding vehicle movements at Hardwick Interchange. Material extraction to be phased such that no more than one Silica site at any one time will transport material by road.

AOS F - North of Stow Bardolph
Subject to submission of Transport Assessment including delivery of acceptable highway improvements. Northern site, access via Runcton Road, widening may be required along with improvements at its junction with A10 to include right turn lane. Southern site, access to be via A10 with right turn lane with suitable levels of visibility. Movement of material using off-highway routes, or conveyor/pipeline etc. preferred. Should material be conveyed by highway, a suitable access to the processing facility shall be provided shall be provided at B1145, to an acceptable standard including visibility. Highways England should be consulted regarding vehicle movements at Hardwick Interchange. Material extraction to be phased such that no more than one Silica site at any one time will transport material by road.

AOS I - East of South Runcton
Subject to submission of Transport Assessment including delivery of acceptable highway improvements. Runcton Road would require widening along with improvements at its junction with A10, or A134 to include right turn lane. Movement of material using off-highway routes, or conveyor/pipeline etc. preferred. Should material be conveyed by highway, a suitable access to the processing facility shall be provided shall be provided at B1145, to an acceptable standard including visibility. Highways England should be consulted regarding vehicle movements at Hardwick Interchange. Material extraction to be phased such that no more than one Silica site at any one time will transport material by road.

AOS J - East of Tottenhill
Subject to submission of Transport Assessment including delivery of acceptable highway improvements. Access via A134 to include right turn lane. Movement of material using off-highway routes, or conveyor/pipeline etc. preferred. Should material be conveyed by highway, a suitable access to the processing facility shall be provided shall be provided at B1145, to an acceptable standard including visibility. Highways England should be consulted regarding vehicle movements at Hardwick Interchange. Material extraction to be phased such that no more than one Silica site at any one time will transport material by road.