Representation Summary:

M40.1 Amenity
The site has the potential to cause emissions of PM10 and PM2.5 which can affect the health and amenity of local residents.
There is a residential property within the site. The next nearest residential property is 23m from the site boundary. There are 88 sensitive receptors within 250m of the site boundary and 25 of these are within 100m of the site boundary. The settlement of East Winch is 23m away. However, I have noted that the part of the site nearest to East Winch is not proposed to be extracted. Therefore, the nearest residential property is 84m from the extraction area and there are 54 sensitive receptors within 250m of the proposed extraction area (three of these are within 100m of the extraction area).
A planning application for mineral extraction at this site must include noise, vibration, dust and air quality assessments, plus mitigation measures to minimise harmful emissions to air and address appropriately any human health or amenity impacts. Additionally the cumulative impacts of nearby allocations MIN06 and WS5 need to be included.
The control and mitigation of dust at this site should be discussed between the operator and the LA Environmental Health Department before an application is submitted. Matters that may need to be explored are:
* the existing dust climate at the locality;
* the need for, and scope of, a dust assessment study to be conducted by the operator prior to a detailed design.
* the potential for different site activities to emit dust and their relationship to residential properties and other sensitive uses;
* how the layout of the site could minimise impacts; and the proposed methods of mitigation and control of dust generating activities such as buffer zones.
It must be ensured that the preparation or use of the site will not result in an exceedance of the national air quality objectives, or an AQMA may need to be declared.
Boundary dust measurement may need to be conducted, due to the close proximity of residential properties to the proposed site, to ensure there are no breaches of national air quality objectives.
Without appropriate mitigation of air pollution from the site, human health could be impacted, thus making the site allocation unsuitable.
Additionally we welcome the requirement within Policy MIN 40 that a scheme of phased working should be submitted prior to development to aid in the mitigation of cumulative emissions.

M40.2 Highway Access
It is proposed that the site will be accessed via the established internal haul route through the existing adjacent extraction area. Mineral would be taken from the site to the processing plant at Leziate using the internal haul route. The majority of processed mineral will leave the processing plant through the onsite railhead. The road transport of mineral would leave the processing plant via the existing access onto Station Road. The site is not within an AQMA.
There is a potential for air quality impacts on residential amenity including air pollution emission from transportation and cumulative effects from Min 06 and WS5. These will need to be assessed within any planning application, given there may be an increase in vehicle movements, and mitigation methods identified, if appropriate.

M40.15 Flood Risk
The site has a low probability of flooding from surface water, with one small location of surface water pooling in a 1 in 1000-year rainfall event. We therefore have no concerns

M40.16 Hydrogeology
We have no concerns regarding groundwater contamination

M40.17 Water Framework Directive
I note that the potential exists for silt ingress to the Mintlyn Stream from material transported by HGV on the haul route, unless conditions are required. Due to the continued use of the existing haul route, the conditions regarding dust in relation to the haul route should be replicated in any future planning permission for MIN 40 to mitigate against watercourse contamination

Full text:


Environmental Quality and Community Safety and Neighbourhood Nuisance Comments on Mineral Site Specific Allocations October 2019

Summary:
If sites have to be progressed to the planning application stage, we would hope that sites furthest from residential dwellings are looked at primarily, as this could ensure that the impact on residential health and amenity is negligible. Clearly these sites would be preferred by us, if needed at all.
Submitted noise assessments and air quality/dust assessments should consider and include mitigation measures to deal appropriately with any potential health impacts, such as operational practices, separation/standoff areas and screening and/or bunding in line with Development Management Policies DM12 and DM13.
These allocated sites have been reviewed in line with Development Management Policies DM12, DM13, and DM15 as detailed within Norfolk Minerals and Waste Development Framework.

Lighting:
Lighting is not included in the document as this is generally something which can be considered at any proposed planning application stage; however we would hope that any proposed lighting for site security and worker safety would be carefully considered prior to the planning stage so details can be submitted with any planning application. We would assume lighting would be pole mounted in elevated positions, and therefore the throw and spread of this should be assessed to ensure that there is no impact on residents. Light should be contained within the confines of sites and positioned appropriately. If necessary lighting is located near dwellings, this should be angled away and hooded/cowled to prevent any adverse impact on residents.

Vibrations:
The potential impact from vibrations should also be considered at any future planning stage, if sites are chosen close to residential receptors - including vibrations from site operations and associated transportation of extracted materials.

Soil Stripping:
Soil stripping operations must be effectively controlled through mitigation methods (e.g. buffer zones and bunding) to reduce fugitive emissions, which pose short term health impacts on nearby residents. These mitigation measures must be included in any future planning application.

Haul Roads:
Fugitive emissions from haul roads need to be addressed in any future planning application, with mitigation planned where necessary such as wheel washing.

[see attached table for comments on individual sites]

Environmental Quality and Community Safety and Neighbourhood Nuisance Comments on Waste Site Specific Allocations October 2019

Summary:
If sites have to be progressed to the planning application stage, we would hope that sites furthest from residential dwellings are looked at primarily, as this could ensure that the impact on residential health and amenity is negligible. Clearly these sites would be preferred by us, if needed at all.
Any future applications for waste sites should be accompanied by noise, odour, dust, and air quality management schemes, which should identify potential sources and mitigation/control measures to prevent nuisance issues and health impacts (e.g. emissions from as gas flaring).
Where sites are likely to be illuminated for safety/security, lighting plans and details should also be submitted which should include where lights will be located, their heights and angle/orientation, the type of lighting and the throw and spill of light across the site, and measures to ensure light spill is contained within site boundaries.
These allocated sites have been reviewed in line with Development Management Policies DM12, DM13, and DM15 as detailed within Norfolk Minerals and Waste Development Framework

Existing Waste Site Specific Allocation Policies:
We note that WAS 05, WAS 25, WAS 36, WAS 40, WAS 37, WAS 45 and WAS 65 are no longer required and would therefore be deleted. There is therefore no risk to residential amenity from these sites.

Odour:
An odour impact assessment should be included within any future planning applications for allocated waste sites, along with suitable mitigation measures where appropriate.

Climate Change:
Climate change mitigation should be considered with regards to methane emissions (a greenhouse gas) released from allocated landfill sites.

[see attached table for comments on individual sites]